Shore Power & AMP Retrofit Services
Engineered to IEC/IEEE 80005-1, sized to the vessel's real berth load and installed inside the dock window. Shore power is our strongest specialization within marine electrical work.
More than a cable and a socket.
Shore power — Alternative Maritime Power (AMP), onshore power supply (OPS) or cold ironing, depending on who is speaking — lets a vessel stop her auxiliary engines at berth and take electricity from the quay. On the vessel side that means a high-voltage shore connection, a transformer sized to the berth load, a cable management system, and protection, earthing and interlocking that meet IEC/IEEE 80005-1.
It is a retrofit of the vessel's electrical system: the connection changes the single-line diagram and lands on the main switchboard. We start from that switchboard and the vessel's actual at-berth load, then design the conversion around the existing system rather than a template. Our guide to what an AMP retrofit involves goes into the scope in more depth.
What the conversion has to get right
From the first survey to a vessel that can plug in.
Survey and berth load
The existing switchboard, the space available and the real at-berth load — measured or reconstructed — before anything is specified. That number sizes the transformer, the cable and the breaker.
HV shore connection
The high-voltage shore connection arrangement, typically 6.6 or 11 kV, designed to IEC/IEEE 80005-1.
Transformer and frequency conversion
A transformer sized to the berth load, and 50/60 Hz frequency conversion where the vessel and the grid differ — on board or ashore.
Cable management system
Cable handling that suits the berths the vessel actually calls at: tidal range, ranging on the lines and safe disconnection.
Protection, earthing and interlocking
The earthing arrangement, coordination between shore and ship protection, and interlocking that stops the shore supply being paralleled with running generators outside a controlled transfer.
Drawings and documentation
Design drawings and documentation prepared for review by the vessel's class society ahead of the work.
Installation
Installation inside the dock window, sequenced with the rest of the yard's work on the vessel.
Testing and commissioning
Insulation and function tests and commissioning, so the vessel leaves able to plug in.
Each vessel type, its own problem
The connection is standard; the engineering problem changes with the ship.
- Container ships — a reefer load that changes call by call and peaks in hot weather
- Tankers — siting the connection and the cable route clear of hazardous areas
- Bulk carriers and general cargo — long berth stays and cargo gear on deck
One system, several names
The terms are used interchangeably; the engineering behind them is the same.
- AMP — Alternative Maritime Power
- OPS — onshore power supply
- Cold ironing
- HVSC — high-voltage shore connection (IEC/IEEE 80005-1)
- LVSC — low-voltage shore connection (IEC/IEEE 80005-3)
From survey to plug-in
The schedule is planned backwards from the dock date.
- 01
Survey
Survey and load measurement
The switchboard, the available space and the at-berth load are surveyed on board.
- 02
Engineer
Engineering and documentation
The connection is designed to 80005-1, drawings go for class review, and long-lead items such as the transformer are ordered against the dock date.
- 03
Deliver
Installation and commissioning
The system is installed in the dock window, tested and commissioned, ready to connect.
OOCL Montreal: AMP at Sefine Shipyard
In 2026 Orion Marine delivered the AMP shore power electrical scope on the 4,402 TEU container ship OOCL Montreal, during a combined yard period at Sefine Shipyard. The work ran to the yard's dock schedule, and the vessel left commissioned — able to shut down her auxiliary engines wherever a quay offers the connection.
Read the case studyFurther reading on shore power
- Retrofit & ModernizationShip electrical retrofits: obsolete drives and switchboard parts replaced, distribution and controls modernised, shore power integrated into the existing plant.
- Marine Electrical ServicesMarine electrical engineering, installation, retrofit, repair and shore power for vessels in service — in shipyards, ports, on board and offshore.
Questions about shore power
- Does the vessel need a high- or low-voltage connection?
- Connection voltage depends on the vessel's berth demand and existing distribution. IEC/IEEE 80005-1 covers high-voltage shore connection, while IEC/IEEE 80005-3 covers low-voltage shore connection for ships requiring up to 1 MVA at berth. The published scope of Part 1 says high-voltage connection is expected to be practicable for ships requiring 1 MVA or more, or ships with a high-voltage main supply. The vessel and the ports she serves determine the final arrangement.
- When do vessels need shore power?
- In the EU, FuelEU Maritime requires containerships and passenger ships above 5,000 gross tonnage to use shore power at berth from 2030 in ports covered by AFIR Article 9, subject to the regulation's exceptions. AFIR separately sets the related shore-side supply target. Other regions have their own rules. Our guide to the 2030 deadlines explains the EU scope.
- How long does a shore power retrofit take?
- It depends on the vessel and on what can be prepared before the docking. Long-lead items such as transformers and frequency converters have to be ordered against the dock date, so we plan the schedule backwards from it during scoping.
Ready to plug in at berth?
Send us the vessel and the dock window you're working towards. We'll scope the conversion against her real berth load.