Shore power, also called Alternative Maritime Power (AMP), onshore power supply (OPS) or cold ironing, lets a vessel shut down her auxiliary engines at berth and take her electrical load from the quay. On the vessel it is a retrofit of the electrical system: a new source of supply connected to the main switchboard, with its own protection, interlocking and controls. This guide sets out the parts of that scope in the order they are decided and points to the detailed guide for each.
The scope at a glance
- Berth load: how much power the vessel draws alongside
- Connection: high or low voltage, and where the connection point sits
- Frequency: whether the supply in the vessel's ports matches her own
- Cable management: from the vessel or from the quay
- Switchboard integration: transformer, incoming breaker, protection, earthing and interlocking
- Control and monitoring
- Drawings and class review
- Installation, testing and commissioning
Berth load comes first
The first question is how much power the vessel actually draws alongside, and how that varies with season and cargo. That figure drives the ratings of the transformer where fitted, the cable and the shore incoming breaker. It is established from representative measurements or reconstructed from the vessel's load analysis; it is not simply read from generator nameplates. Our guide to shore power load assessment explains the method.
The connection: voltage, frequency and the standard
Connection voltage depends on the berth demand and the vessel's existing distribution. IEC/IEEE 80005-1 covers high-voltage shore connection, while IEC/IEEE 80005-3 covers low-voltage shore connection. Our guide to IEC/IEEE 80005-1 on the ship side explains the high-voltage standard's published scope.
Frequency is the other variable. Many vessels run at 60 Hz and the European grid is 50 Hz. Where a vessel and her regular ports do not match, a frequency converter is needed, on the quay if the port provides one or on board if it does not. A converter on board is large, needs cooling and changes the cost of the retrofit, so the question is settled with the ports before the on-board scope is fixed.
Cable management depends on the berths
Whether the cable is handled from the quay or from the vessel depends on the terminals she calls at. Where the terminal provides cable management, the vessel needs her connection point in the right place. Where it does not, a reel or other handling equipment goes on board, with the deck space and the structure to carry it. The vessel's actual trading pattern decides this, not a general preference.
Integration into the switchboard
The shore supply reaches the vessel's distribution as a new incoming source. Depending on the arrangement, the work can include a transformer, an incoming breaker, fault-level and protection studies, earthing, and interlocking between shore and generator sources. The existing board and each operating mode have to be checked together. The detail is covered in shore power switchboard integration.
Drawings and class review
A shore connection changes the vessel's electrical drawings and normally requires class review of the modification. The submission set and review time therefore belong in the project schedule before installation begins. Which ships and ports the EU rules apply to is covered in our guide to the 2030 shore power rules.
Fitting the work into a yard period
Much of the work may be prepared before the final shutdown, depending on the vessel: cable routes, foundations and installation of major equipment. Busbar connections, penetrations, heavy lifts and other shutdown-dependent tasks are then aligned with the yard or port window. Long-lead equipment is ordered against that programme. On OOCL Montreal, Orion Marine delivered the AMP electrical scope at Sefine Shipyard in 2026 within a combined yard period.
Testing and commissioning close the job
The installation is verified before and during energisation: dead-circuit checks first, then controlled energisation, protection and interlock tests, alarms and the designed transfer sequence. The broader method is described under testing and commissioning. The job is closed only after the installed system has been commissioned for its intended operating arrangement.